信息产业部万寿路机关办公楼工程结构施工难点解决方案

2009-08-12

摘  要:信产部办公楼场地异常狭小、施工环境差,工期紧、质量目标高,作者在该工程中重点解决钢结构吊装的大型机具,为提高塔吊的效率解决水平运输问题创造场内东西向通道,突破场地瓶颈。

Engineering Solution for Structure Construction Difficult of the Office Building of Ministry of Information Industry

LIU Yong-chuan1, GOU Li-chun2

(1.The Third Construction Engneering Company Ltd. of Beijing, Beijing 100055,China; 2.Qinhuangdao Qin Star Project Management Company Ltd.,,Qinghuangdao 066000,China)

Abstract: The office building of ministry of information industry is abnormal small, and the construction environment is bad. However, the construction is short for time but high standard for quality. The author focuses on the engineering of large-scale steel hoisting equipment, in order to improve the efficiency of tower cranes to resolve transportation problem by getting through the channel from east to west, so that to break through space bottlenecks.

Key words: tower crane; channel; hoisting; welding; winter construction